PGE and Ørsted have signed an agreement for the transportation and installation of offshore transformer stations for the Baltica 2 project
PGE Group and Ørsted have selected a supplier to transport to the area of the future farm and install offshore substations for the Baltica 2 project, one of the two stages of the Baltica Offshore Wind Farm. The successful bidder Seaway7 is a world leader in the implementation of offshore wind projects. It will use both heavy lift and heavy transportation vessels to carry out the transportation and installation of the offshore substations. Work is scheduled to begin in 2026. The four offshore substations will be designed, built, and commissioned by the Semco/PTSC consortium. PGE and Ørsted have already contracted…